1. Arterial Road Topo in Modimolle - client - KST- completed. Click Here To View Files
2. D4190 Road - As-built compilation: Drawing production for close out report and final certificate of completion on behalf of client (see drawing) - completed .
Click Files Below To View D4190 Road Project Data
Revision 2-D4190 Plan and Section - (1)
Revision 2-D4190 Plan and Section - (2)
Revision 2-D4190 Plan and Section - (3)
Revision 2-D4190 Plan and Section - (4)
Revision 2-D4190 Plan and Section - (5)
Revision 2-D4190 Plan and Section - (6)
Revision 2-D4190 Plan and Section - (7)
Revision 2-D4190 Plan and Section - (8)
Revision 2-D4190 Plan and Section - (9)
Revision 2-D4190 Plan and Section - (10)
Revision 2-D4190 Plan and Section - (11)
Revision 2-D4190 Plan and Section - (12)
Revision 2-D4190 Plan and Section - (13)
Revision 2-D4190 Plan and Section - (14)
Revision 2-D4190 Plan and Section - (15)
Revision 2-D4190 Plan and Section - (16)
3. Engineering Services provision for Township Extension 78 Seshego (428 stands). Turnkey survey services (Design, construction and close-out surveys) for: gravel road network, sewer and water reticulation - client- Insig Consultancy - completed .
Click Files Below To View Project Data Extension 78 Seshego
Survey Report for Roads & Water Ext 78
Survey Report for Sewer Reticulation Ext 78
4. Aerial Survey for Floodline Analysis of New Township Establishment-Thohoyandou - private client - to be initiated soon.
5. Engineering Services provision for Township Extension 134 Seshego (1115 stands). Build-design technique utilised (see the long section). Quality control and assurance (drone applications included) and close-out surveys for: gravel road network, sewer and water reticulation - client- Insig Consultancy - on-going.
Click Files Below To View - Extension 134 Seshego
Bulk Sewer MH7-2 to MH122 ext 134
Bulk Sewer MH122 to MH2 ext 134
Bulk Sewer to Pump Station ext 134
Layout Bulk Sewer MH7-2 to MH2 ext 134
Layout Bulk Sewer to Pump Station rev1 MH2 to Sump ext 134
6. Engineering Services provision for Makhado ext 121, Louis Trichardt (671 stands). Beacon relocation, Quality control and assurance (includes monitoring using drone technology) and close-out surveys for: gravel road network, sewer and water reticulation - client- Insig Consultancy - almost complete.
Click Files Below To View - Ext 121, Louis Trichardt
7. Polokwane water treatment works - client- Zerbacraft - on going. GCC contract (in this contract I am working within the consortium of Zerbacraft)
Click Files Below To View - Polokwane water treatment works
SandRiver WTW Benchmark Report
SandRiver WTW Preliminary Survey Report